PMP passing score: what PMI publishes, and how the domain ratings work
By the examtwin team ·
The short answer
PMI does not publish a PMP passing score, a percentage or a number of questions to get right. Your score report says pass or fail and gives a rating for each of the three domains: Above Target, Target, Below Target or Needs Improvement. PMI sets the passing standard by psychometric analysis of what a qualified project manager should know, and counts only the 170 scored questions.
- Passing score
- Not published
- Result
- Pass or fail
- Per domain
- Four ratings
- Scored questions
- 170 of 180
- Result on the day
- Preliminary
- Attempts
- 3 in the 1-year eligibility
How PMI decides a pass
PMI’s certification handbook calls its exams criteria-based: the passing standard is whether you meet the level of a qualified person in the role, for the PMP an experienced project manager. Each scored question is treated as a sample of your proficiency, and PMI compares the whole picture with the standard. Unscored pretest questions do not count.
For the PMP, the result shown at the end of your session is preliminary until PMI confirms it; the report is online within 10 business days.
The four domain ratings
| Rating | Meaning |
|---|---|
| Above Target | Your performance in the domain is above the standard |
| Target | Your performance meets the standard |
| Below Target | Slightly below the standard |
| Needs Improvement | Well below the standard |
- Above Target
- MeaningYour performance in the domain is above the standard
- Target
- MeaningYour performance meets the standard
- Below Target
- MeaningSlightly below the standard
- Needs Improvement
- MeaningWell below the standard
PMI’s handbook says the report gives the overall pass or fail and diagnostic information for each domain; the four rating names are those candidates see on their reports. The ratings are a diagnosis for each domain (People, Process, Business Environment); the pass or fail is decided on the exam as a whole, so a weak domain does not by itself mean a fail.
How examtwin estimates a pass
Because PMI publishes no cut score, examtwin’s practice report uses stated bands: a domain is Above Target from 80% of its points, Target from 65%, Below Target from 50%, and Needs Improvement below that; the pass estimate needs 65% of all scored points. Matching and pull-down questions earn part of a point for each part right.
If you do not pass
You may take the exam up to three times within your one-year eligibility period. After three attempts without a pass you wait a year from the last one before applying again. Practise with the free full-length practice exam, which rates each domain the same way.
See your domain ratings
A free full-length exam, no card.
Questions people ask
What is the passing score for the PMP exam?
PMI does not publish one. The result is pass or fail, set by psychometric analysis against the standard of an experienced project manager, with a rating for each domain.
What percentage do you need to pass the PMP?
PMI does not publish a percentage. Prep courses often suggest aiming for 70% or more on full-length practice exams; examtwin’s estimate uses 65% of the scored points.
Can you pass the PMP with Below Target in one domain?
The pass or fail is decided on the whole exam, and the domain ratings are a diagnosis. A candidate can pass with one domain below target if the others are strong.
Do the 10 pretest questions count?
No. PMI evaluates candidates on the 170 scored questions only, and you cannot tell which questions are pretest.
Sources · checked 21 November 2026
examtwin is an independent practice platform and is not affiliated with, endorsed by or approved by PMI (Project Management Institute) or Pearson VUE. PMI, PMP and PMBOK are marks of the Project Management Institute, Inc. The questions are examtwin’s own, and results are practice estimates, not official results.