12 free PMP practice questions with answers and explanations (2026 outline)
By the examtwin team ·
The short answer
Here are 12 free PMP practice questions written to PMI’s July 2026 content outline: four from each of the three domains, People, Process and Business Environment, 8 of them set on agile or hybrid projects, in the exam’s types: situational multiple choice, multiple response, matching, pull-down lists and questions on a chart. Each opens to its answer and an explanation that names the principle behind it. They are examtwin’s own and never appear in its practice exams.
- Questions
- 12, all explained
- Domains
- All 3 of the 2026 outline
- Agile or hybrid
- 8 of 12
- To read them
- No sign-up
- Full exam
- 180 questions, free
- Outline
- PMI, July 2026
People (33% of the exam)
Question 1 · Multiple choice · People, task 1.1 (Develop a common vision) · Agile
An agile team is building a fitness app for adults over 65. A newly hired marketing director asks the team to add game features aimed at teenagers, saying they will grow downloads. The team asks the project manager what to do. What should the project manager do NEXT?
A.Add the features to the top of the backlog because marketing drives growth
B.Have the product owner and director weigh the request against the vision
C.Decline the request politely because it falls outside the product vision
D.Ask the team to estimate the features so the director can see the cost
Answer and rationale
B. Have the product owner and director weigh the request against the vision
The product vision is the reference for deciding whether new ideas belong, and the product owner owns that decision, so the project manager should bring the product owner and the director together to weigh the request against the agreed vision. If they conclude the target market has truly changed, the vision can be updated openly rather than drifting. Adding the features straight to the top bypasses the product owner. Declining outright takes a decision that is not the project manager's and may ignore a real business change.
PMBOK® Guide, 7th ed., principle: Focus on value
PMBOK® Guide, 8th ed., principle: Focus on value
Agile Practice Guide: Backlog preparation and refinement
Question 2 · Multiple choice, graphic-based · People, task 1.3 (Lead the project team) · Hybrid
A project manager reviews last week's hours for the five analysts on a hybrid data platform migration. What is the BEST action for the project manager?
A.Praise Analyst C at the next team meeting as an example of commitment
B.Move half of Analyst C's tasks to Analyst D and Analyst E today
C.Talk with Analyst C about the workload and how it could be shared
D.Ask Analyst C's functional manager to approve overtime for the coming weeks
Answer and rationale
C. Talk with Analyst C about the workload and how it could be shared
Analyst C worked 61 hours, far above the 44-hour average, which is a warning sign for burnout and for a single point of failure. The project manager should first talk with Analyst C to understand why, then work with the team on spreading the load. Praising the overtime publicly rewards an unsustainable pattern. Moving tasks immediately acts before understanding which work can be shared, and approving overtime accepts the problem rather than solving it.
PMBOK® Guide, 7th ed., principle: Create a collaborative project team environment
PMBOK® Guide, 8th ed., principle: Integrate sustainability
PMBOK® Guide, 8th ed., performance domain: Resources
Agile Practice Guide: Team composition and the self-organizing, cross-functional team
Question 3 · Multiple response (choose 2) · People, task 1.6 (Manage stakeholder (customer) expectations) · Hybrid
A hybrid ERP rollout delivers the finance modules on a fixed plan, with reporting features added in sprints. The finance department, an internal customer, expected the new system to speed up its month-end close. Which measures would BEST show whether finance is getting the outcome it expected?
A.Number of user stories the team has completed
B.Hours logged by the project team each month
C.Days needed to close the books each month, compared with before go-live
D.Finance users' satisfaction scores collected after each release
E.Number of status reports issued to the finance director
F.Percentage of the project budget spent to date
Answer and rationale
C. Days needed to close the books each month, compared with before go-live
D. Finance users' satisfaction scores collected after each release
Whether an internal customer gets the outcome it expected is shown by measures of that outcome and of the customer's own experience, not by measures of project activity. The number of days to close the books compared with before go-live tracks the very benefit finance wanted, and regular satisfaction scores show how users feel about what they are receiving. Stories completed, hours logged and budget spent describe the project's effort and outputs. The number of status reports shows communication volume, not value delivered.
PMBOK® Guide, 7th ed., principle: Focus on value
PMBOK® Guide, 7th ed., performance domain: Measurement
PMBOK® Guide, 8th ed., principle: Focus on value
Agile Practice Guide: Measuring agile work: burn charts, velocity, cycle time, flow
Question 4 · Matching · People, task 1.2 (Manage conflicts) · Predictive
A project manager building a regional distribution center hears the following complaints in one week. Match each complaint to its source of conflict.
Places
1. Two engineers disagree on whether steel or timber framing will carry the roof load
2. Marketing wants the opening moved up a month; the test lead says that leaves no time to commission
3. The racking crew and the electricians both need the only certified forklift operator next Tuesday
4. The site team keeps skipping the three-signature purchase form that finance insists on
Answers
Answer and rationale
Two engineers disagree on whether steel or timber framing will carry the roof load → Technical opinions
Marketing wants the opening moved up a month; the test lead says that leaves no time to commission → Schedule
The racking crew and the electricians both need the only certified forklift operator next Tuesday → Scarce resources
The site team keeps skipping the three-signature purchase form that finance insists on → Administrative procedures
Naming the source of a conflict helps the project manager choose how to handle it. A disagreement over framing is a difference of technical opinion, best settled with data and expert input. Pressure to open earlier against commissioning time is a schedule conflict, and two crews needing one operator is a conflict over scarce resources. Friction over a purchase form is about administrative procedures, which often calls for clarifying why the rule exists rather than a personal intervention.
PMBOK® Guide, 7th ed., performance domain: Team
PMBOK® Guide, 7th ed., principle: Create a collaborative project team environment
PMBOK® Guide, 8th ed., performance domain: Resources
Process (41% of the exam)
Question 5 · Multiple choice · Process, task 2.1 (Integrated plan and delivery approach) · Agile
A start-up is building a meal-planning app for people with diabetes. Nobody yet knows which features users will pay for, and the founders expect to learn a lot from the first users. An investor on the board asks the project manager for a 12-month plan listing every feature with its delivery date. What is the BEST response?
A.Explain the uncertainty and offer a roadmap with short iterations and early releases
B.Prepare the detailed 12-month plan and add 20% contingency to every date
C.Run a three-month requirements study to remove the uncertainty before planning
D.Ask the developers to choose their own approach and report back to the board later
Answer and rationale
A. Explain the uncertainty and offer a roadmap with short iterations and early releases
High uncertainty about what users value calls for an adaptive approach in which each release tests assumptions and shapes the next. A goal-based roadmap still gives the board a view of direction and timing while being honest that the feature list will change as evidence arrives. A fully dated feature plan with padding gives false precision, and a long study delays the learning that only real users can provide. Leaving the board out of the decision ignores a key stakeholder's legitimate need for information.
PMBOK® Guide, 7th ed., principle: Navigate complexity
PMBOK® Guide, 7th ed., performance domain: Development approach and life cycle
PMBOK® Guide, 8th ed., principle: Focus on value
Agile Practice Guide: Choosing a life cycle: predictive, iterative, incremental, agile
Question 6 · Multiple choice, graphic-based · Process, task 2.2 (Develop and manage scope) · Predictive
Halfway through a predictive project to build a new courthouse, the project manager analyzes the 44 change requests raised so far, shown by cause. Most of the missed needs came from court staff, who were not interviewed when requirements were gathered. What should the project manager do NEXT?
A.Tighten the change control process so that fewer requests are approved
B.Freeze the scope for the rest of the project
C.Add a contingency reserve sized to the rate of change requests
D.Have court staff review the remaining requirements with the team
Answer and rationale
D. Have court staff review the remaining requirements with the team
Half of the change requests trace back to one cause: a stakeholder group whose needs were never collected. Bringing court staff in to review the remaining requirements tackles that root cause and should reduce later changes, which are expensive in construction. Tightening approval or freezing scope would simply leave real needs unmet and store up problems for handover. Extra contingency pays for the symptom without fixing the reason requirements were missed.
PMBOK® Guide, 7th ed., performance domain: Stakeholders
PMBOK® Guide, 8th ed., performance domain: Scope
PMBOK® Guide, 7th ed., principle: Effectively engage with stakeholders
Question 7 · Multiple response (choose 2) · Process, task 2.3 (Help ensure value-based delivery) · Hybrid
A telecom company's hybrid program is building a self-service portal to reduce calls to its contact center. The sponsor asks the project manager to propose measures that will show whether the portal is delivering its intended benefit. Which measures should the project manager propose?
A.Number of portal pages published
B.Story points delivered per sprint
C.Drop in calls on the topics the portal covers
D.Number of features released each quarter
E.Share of customers completing tasks online without help
F.Hours the team has spent on the portal
Answer and rationale
C. Drop in calls on the topics the portal covers
E. Share of customers completing tasks online without help
Benefit measures should track the outcome the business wants, so the fall in calls on covered topics and the share of customers who complete tasks online unaided show directly whether the portal is taking load off the contact center. Pages published, story points, features released and hours spent all describe the team's output or effort, which can rise while the benefit stays flat. Choosing outcome measures keeps the program focused on value rather than activity.
PMBOK® Guide, 7th ed., performance domain: Measurement
PMBOK® Guide, 8th ed., principle: Focus on value
Agile Practice Guide: Measuring agile work: burn charts, velocity, cycle time, flow
Question 8 · Pull-down list · Process, task 2.4 (Plan and manage resources) · Predictive
A project manager on a predictive plant expansion is describing four ways of adjusting the plan. Select the technique each one describes.
| Action | Technique |
|---|---|
| Delay a non-critical activity within its float to flatten a peak in demand | [Resource leveling / Resource smoothing / Crashing / Fast-tracking] |
| Delay activities beyond their float because one specialist can do only one at a time | [Resource smoothing / Fast-tracking / Resource leveling / Crashing] |
| Add a second crew to a critical activity to shorten it | [Crashing / Resource leveling / Fast-tracking / Resource smoothing] |
| Start a critical activity before its predecessor finishes | [Resource smoothing / Crashing / Resource leveling / Fast-tracking] |
Answer and rationale
Delay a non-critical activity within its float to flatten a peak in demand · Technique: Resource smoothing
Delay activities beyond their float because one specialist can do only one at a time · Technique: Resource leveling
Add a second crew to a critical activity to shorten it · Technique: Crashing
Start a critical activity before its predecessor finishes · Technique: Fast-tracking
Smoothing moves activities only within their float, so peaks flatten without changing the end date, while leveling resolves overallocations even if that means delaying work beyond its float and moving the finish. Crashing adds resources to critical activities to shorten them at extra cost, and fast-tracking overlaps activities that would normally run in sequence, accepting more risk. Knowing which technique changes the end date, the cost or the risk helps the project manager pick the right one.
PMBOK® Guide, 7th ed., performance domain: Planning
PMBOK® Guide, 8th ed., performance domain: Resources
PMBOK® Guide, 8th ed., performance domain: Schedule
Business Environment (26% of the exam)
Question 9 · Multiple choice · Business Environment, task 3.1 (Define and establish project governance) · Agile
A startup's sponsor asks the agile project manager to have the team hard-code the results of an unfinished recommendation feature so that it looks complete in next week's demo to investors. The investors are deciding on the company's next funding round. What should the project manager do?
A.Hard-code the results, since demos for investors are usually simplified
B.Present the feature as complete and finish it before the investors use it
C.Show its real state, or present a mock-up that is clearly labeled as one
D.Refuse to take part in the demo and report the sponsor to the board
Answer and rationale
C. Show its real state, or present a mock-up that is clearly labeled as one
Investors will make a funding decision on what they see, so presenting a hard-coded feature as working would mislead them, whatever the intent. The responsible course is to show the feature's real state, or a mock-up plainly presented as a design, together with the plan for finishing it, and to discuss this openly with the sponsor. Faking the result, or claiming it is complete and racing to finish later, is deception that can harm the company and everyone involved. Refusing and going straight to the board skips the direct conversation with the sponsor, who may well accept an honest alternative.
PMBOK® Guide, 7th ed., principle: Be a diligent, respectful and caring steward
PMBOK® Guide, 8th ed., principle: Lead accountably
Agile Practice Guide: Daily standups, reviews and demonstrations
Question 10 · Multiple choice, graphic-based · Business Environment, task 3.2 (Plan and manage project compliance) · Agile
A government agency's agile team builds a benefits application that must meet the national web accessibility standard. The team checks accessibility only in the week before each quarterly release; the defects found at each release audit are shown. The last release was delayed to fix them. What is the BEST action?
A.Add a dedicated accessibility hardening sprint before each quarterly release
B.Hire an external auditor to check the application more thoroughly at each release
C.Add accessibility criteria and checks to the definition of done for every story
D.Ask the product owner to create an accessibility epic for the next quarter's work
Answer and rationale
C. Add accessibility criteria and checks to the definition of done for every story
Defects are rising because accessibility is inspected at the end instead of built in. Putting accessibility criteria and checks into the definition of done means every increment is verified as it is built, so problems are caught when they are cheap to fix and compliance becomes continuous. A hardening sprint or a stronger end-of-quarter audit keeps the same late-detection pattern, and a one-time epic treats a standing requirement as a single piece of work. Building quality in, rather than inspecting it at the end, is how an agile team meets an ongoing compliance obligation.
PMBOK® Guide, 7th ed., principle: Build quality into processes and deliverables
PMBOK® Guide, 8th ed., principle: Embed quality
Agile Practice Guide: Team composition and the self-organizing, cross-functional team
Question 11 · Multiple response (choose 2) · Business Environment, task 3.5 (Plan and manage risk) · Agile
A newly formed Scrum team is building a route-planning app for a logistics firm. The sponsor worries that risks will go unmanaged because the team keeps no separate risk register. Which actions would BEST build risk management into the team's normal way of working?
A.Hold a monthly risk workshop led by the project manager outside the sprints
B.Discuss emerging risks in refinement and add risk-reduction items to the backlog
C.Ask the product owner to approve each risk before it is recorded
D.Write a full risk management plan before the first sprint begins
E.Keep a visible risk board that the team reviews at its daily stand-up
F.Make the scrum master the owner of every identified risk
Answer and rationale
B. Discuss emerging risks in refinement and add risk-reduction items to the backlog
E. Keep a visible risk board that the team reviews at its daily stand-up
Agile teams manage risk continuously inside the cadence they already have: refinement surfaces risks and turns responses into backlog items that compete for priority, and a visible board keeps risks in front of the team every day. These practices make risk part of the work rather than a parallel process. A monthly workshop outside the sprints separates risk from the people doing the work, and a long plan up front contradicts the incremental approach. Ownership belongs with whoever is best placed to act, not by default with the scrum master or behind a product owner's approval.
PMBOK® Guide, 7th ed., principle: Optimize risk responses
PMBOK® Guide, 8th ed., performance domain: Risk
Agile Practice Guide: Backlog preparation and refinement
Agile Practice Guide: Daily standups, reviews and demonstrations
Question 12 · Matching · Business Environment, task 3.5 (Plan and manage risk) · Predictive
The project manager for a hospital's new sterile-supply facility is reviewing the planned responses to threats. Match each planned action to the strategy it represents.
Places
1. Drop the unproven robotic sorter from scope so its failure cannot affect the launch
2. Award the HVAC work on a fixed price backed by a performance bond
3. Add a standby steam generator to limit downtime if the main unit fails
4. Set aside a reserve and act only if the linen supplier goes bankrupt
5. Refer a citywide water-quality concern to the hospital's executive board
Answers
Answer and rationale
Drop the unproven robotic sorter from scope so its failure cannot affect the launch → Avoid
Award the HVAC work on a fixed price backed by a performance bond → Transfer
Add a standby steam generator to limit downtime if the main unit fails → Mitigate
Set aside a reserve and act only if the linen supplier goes bankrupt → Accept
Refer a citywide water-quality concern to the hospital's executive board → Escalate
Avoiding a threat changes the plan so the threat can no longer occur, which is what removing the sorter does. A fixed price with a bond moves the financial consequence to the contractor, which is transfer, while a standby generator reduces the impact of a failure, which is mitigation. Holding a reserve and acting only if the event happens is active acceptance, and passing a citywide concern to the executive board is escalation because it lies beyond the project's authority. Exploit and enhance are responses to opportunities, not threats.
PMBOK® Guide, 7th ed., principle: Optimize risk responses
PMBOK® Guide, 7th ed., performance domain: Uncertainty
PMBOK® Guide, 8th ed., performance domain: Risk
How to use these questions
Answer before you open the explanation, and read it even when you were right. PMP questions turn on what to do first or what is best in a situation; the explanation says why the other actions come too early, too late or from the wrong person, which is what the next question will test.
The real exam is 180 questions in 240 minutes, opening with case studies. To practise that, take the free full-length PMP practice exam, or the 60-question mini test for a shorter sitting.
Take a full practice exam
Free, no card. Start without an account.
Questions people ask
Are these real PMP questions?
No. They are examtwin’s own, written to PMI’s 2026 content outline. PMI’s exam questions are confidential, and recalled questions from braindump sites break its exam security rules.
Are these questions for the new 2026 PMP exam?
Yes. They follow the outline PMI has used since 9 July 2026: People, Process and Business Environment weighted 33/41/26%, about 60% agile or hybrid, and the new types such as questions on a chart.
How are PMP questions different from a textbook quiz?
Almost every question is a short situation that asks what the project manager should do, first or best. Knowing the terms is not enough: you need the order of actions that the PMBOK Guide and the Agile Practice Guide describe.
Sources · checked 21 November 2026
examtwin is an independent practice platform and is not affiliated with, endorsed by or approved by PMI (Project Management Institute) or Pearson VUE. PMI, PMP and PMBOK are marks of the Project Management Institute, Inc. The questions are examtwin’s own, and results are practice estimates, not official results.